Friday, 31 January 2025: Following over 10 months of uninterrupted electricity supply due to the success of the Generation Recovery Plan, Eskom has encountered a temporary setback. As a result, Stage 3 loadshedding is being implemented from 17:00 today until Sunday midnight. Eskom will give an update on Sunday, 2 February 2025.
“This is a temporary setback, as loadshedding is largely behind us due to structural improvements in the generation fleet,” said Eskom Group Chief Executive, Dan Marokane.
“Over the past seven days, we have experienced several breakdowns that require extended repair times. This has necessitated the use of all our emergency reserves, which now need to be replenished over the weekend,” concluded Marokane.
“The structural improvements and efficiency gain we have made to our coal-fired generation fleet to date are safe and the R16.30 billion saved in diesel spend from 1 April 2024 to 30 January 2025 is also safe,” said Group Executive Generation, Bheki Nxumalo.
“The weekend loadshedding allows for the replenishment of the Open-Cycle Gas Turbines and pumped storage reserves in preparation for next week. We are committed to ensuring that South Africa is in no way returning to the levels of loadshedding that we experienced in 2023,” https://www.eskom.co.za/distribution/wp-content/uploads/2024/11/2024123Vending-outlets.xlsx
Eskom urges the public to help protect the integrity of the power network by reporting any illegal activities to the Eskom Crime Line at 0800 112 722 or via WhatsApp at 081 333 3323.
Progress and delivery of turnaround strategy
Eskom announced its group interim results for the first six months of the 2025 financial year, covering the period 1 April to 30 September 2024, yesterday. The results demonstrate the significant improvement in performance that the organisation has delivered to address South Africa’s energy crisis. The energy availability factor (EAF) of Eskom’s generation plant increased to 62.96% for the period under review (September 2023: 55.27%). The improvement in availability is largely due to a significant decrease of around 4 000MW (which equates to four stages of loadshedding) in unplanned breakdowns and losses (UCLF) to 25.60%, compared to 34.24% in the prior period. EAF exceeded 70% on several occasions during the period under review, with UCLF at times falling below 20%.
We will provide an update on Friday, 7 February 2025, or promptly communicate any significant changes as soon as they occur.
About Eskom and Electricity – Kusile Power Station: Another major coal-fired power station currently under construction.

nickname master
Adrian Gore – Adrian Gore founded Discovery Health in 1992. His company went on to change the health insurance space in SA forever with innovative products such as Vitality. Many insurance companies overseas have now begun to copy the Discovery model and Discovery themselves have taken their products abroad with good success. At the end of 2015, Gore featured at no. 12 on the Sunday Times list of wealthiest businessmen, with R7.2 billion fortune due to his holding in the financial services firm.