You are here: Home / News / Rand Water Station 5 purification plant ensures Gauteng’s water security

Rand Water Station 5 purification plant ensures Gauteng’s water security

4 September 2023 by Guest

Rand Water Station 5 purification plant ensures Gauteng’s water security

Rand Water has been hailed for completing Phase 1 of the 150 megalitres a day (ML/d) Station 5A filtration plant on schedule.

The plant, which is one of Rand Water’s flagship projects, will bring assurance to the sustainability of water supply to the Gauteng province and surroundings.

Water and Sanitation Minister Senzo Mchunu and Deputy Minister David Mahlobo, joined by the Emfuleni Mayor Sipho Radebe, Rand Water Board Chairperson Ramateu Monyokolo, and Rand Water Chief Executive Sipho Mosai, have commissioned the first part of the mega water project situated at the Zuikerbotch Water Treatment Works outside Vereeniging in the Vaal.

Mchunu said there is a great need to increase infrastructure and to ensure that operation and maintenance are undertaken to existing infrastructure, and that Rand Water is doing exactly that.

The Minister commended Rand Water in its forward thinking and keeping its eye on its mandate.

“Whether it is in terms of actual water supply or the maintenance of water and sanitation infrastructure, Rand Water has continued to ensure that it keeps its eye on the mandate. Those of you doubting our commitment as DWS to infrastructure development, forget it. We’re ahead of the curve. It is not a matter of when, but rather where are we today,” Mchunu said.

Rand Water has built the completely new purification plant at the existing Zuikerbosch Plant, referred to as Station 5, in an effort to augment water supply, ensure sustainable water supply, and to meet current and future demands.

The Station 5 plant is divided into two phases (5A and 5B). The completed Phase 1, Station 5A, will produce 150ml/d of potable water, adding to the current available supply by Rand Water to its customers, including Gauteng municipalities, parts of Free State, Mpumalanga and North West provinces, as well as industries.

Upon completion of Phase 2 (Station 5B) at the end of 2024, the plant will add another 450 ML/d, totalling to 600ML/d of water to users.

The purification plant is part of the Rand Water’s capital expenditure projects and seeks to bring more capacity to the water utility’s system to ensure water security to the provinces it supplies.

Speaking at the recent ribbon cutting to officially commission Phase 1 of the newly built Section 5A purification plant, Mchunu emphasised the need for new water infrastructure to address current and future demand of water in the province. 

He said the commissioning of Station 5A is demonstrative of the department’s seriousness about increasing infrastructure capacity.

Mchunu said while the mandate of the sector was to ensure access to clean drinking water and to manage water resources, “one cannot have access to water without the proper infrastructure”.

Since 2019, the Station 5A project has created 871 job opportunities, providing employment to people with diverse skill levels, ranging from unskilled to semi-skilled, and skilled labourers.

The project has also supported more than 48 Small, Medium and Micro Enterprises (SMMEs) with small work packages from the core activities of the 26 projects.

Vision 2030 infrastructure build programme

Monyokolo said the project is part of Rand Water’s Vision 2030 Infrastructure Build Programme and that they are well within their timelines and in some instances, they are ahead.

“… This additional 150ML/d Station 5A programme ensures that there is more than enough water for all our customers and therefore consumers.

“As a board, we have a full and comprehensive understanding of the importance of infrastructure upgrading and refurbishment to ensure uninterrupted bulk water supply to our customers. As we celebrate the 120th year anniversary of our existence, we recognise and embrace inherent challenges that we continue to turn  into opportunities,” Monyokolo said.

Monyokolo also noted some of the challenges faced by the water utility in the implementation of its CAPEX [capital expenditure] projects, which include population growth in its areas of supply, vandalism of infrastructure, encroachment on servitudes, quality of raw water, and non-payment of invoices by customers.

“The porous municipal water reticulation infrastructure also creates a simulated shortage. We are working hard to assist and collaborate with municipalities through the capable leadership of our Minister to mitigate this challenge.”

In February this year, the water utility launched the 210ML/d Vlakfontein Reservoir in the City of Ekurhuleni. The reservoir is post-tensioned concrete, the biggest in the world and is part of the Mapleton Booster system augmentation programme. – SAnews.gov.za

GabiK
Mon, 09/04/2023 – 13:46

353 views

Rand Water has been hailed for completing Phase 1 of the 150 megalitres a day (ML/d) Station 5A filtration plant on schedule.

The plant, which is one of Rand Water’s flagship projects, will bring assurance to the sustainability of water supply to the Gauteng province and surroundings.

Water and Sanitation Minister Senzo Mchunu and Deputy Minister David Mahlobo, joined by the Emfuleni Mayor Sipho Radebe, Rand Water Board Chairperson Ramateu Monyokolo, and Rand Water Chief Executive Sipho Mosai, believe commissioned the first fraction of the mega water project situated at the Zuikerbotch Water Treatment Works outside Vereeniging in the Vaal.

Mchunu said there is a noteworthy need to increase infrastructure and to ensure that operation and maintenance are undertaken to existing infrastructure, and that Rand Water is doing exactly that.

The Minister commended Rand Water in its forward thinking and keeping its eye on its mandate.

“Whether it is in terms of actual water supply or the maintenance of water and sanitation infrastructure, Rand Water has continued to ensure that it keeps its eye on the mandate. Those of you doubting our commitment as DWS to infrastructure development, forget it. We’re ahead of the curve. It is not a matter of when, but rather where are we today,” Mchunu said.

Rand Water has built the completely recent purification plant at the existing Zuikerbosch Plant, referred to as Station 5, in an effort to augment water supply, ensure sustainable water supply, and to meet current and future demands.

The Station 5 plant is divided into two phases (5A and 5B). The completed Phase 1, Station 5A, will produce 150ml/d of potable water, adding to the current available supply by Rand Water to its customers, including Gauteng municipalities, parts of Free State, Mpumalanga and North West provinces, as well as industries.

Upon completion of Phase 2 (Station 5B) at the terminate of 2024, the plant will add another 450 ML/d, totalling to 600ML/d of water to users.

The purification plant is fraction of the Rand Water’s capital expenditure projects and seeks to bring more capacity to the water utility’s scheme to ensure water security to the provinces it supplies.

Speaking at the recent ribbon cutting to officially commission Phase 1 of the newly built Section 5A purification plant, Mchunu emphasised the need for novel water infrastructure to address current and future demand of water in the province. 

He said the commissioning of Station 5A is demonstrative of the department’s seriousness about increasing infrastructure capacity.

Mchunu said while the mandate of the sector was to ensure access to clean drinking water and to manage water resources, “one cannot believe access to water without the proper infrastructure”.

Since 2019, the Station 5A project has created 871 job opportunities, providing employment to people with diverse skill levels, ranging from unskilled to semi-skilled, and skilled labourers.

The project has also supported more than 48 Small, Medium and Micro Enterprises (SMMEs) with small work packages from the core activities of the 26 projects.

Vision 2030 infrastructure build programme

Monyokolo said the project is portion of Rand Water’s Vision 2030 Infrastructure Build Programme and that they are well within their timelines and in some instances, they are ahead.

“… This additional 150ML/d Station 5A programme ensures that there is more than enough water for all our customers and therefore consumers.

“As a board, we maintain a full and comprehensive understanding of the importance of infrastructure upgrading and refurbishment to ensure uninterrupted bulk water supply to our customers. As we celebrate the 120th year anniversary of our existence, we recognise and embrace inherent challenges that we continue to turn  into opportunities,” Monyokolo said.

Monyokolo also noted some of the challenges faced by the water utility in the implementation of its CAPEX [capital expenditure] projects, which include population growth in its areas of supply, vandalism of infrastructure, encroachment on servitudes, quality of raw water, and non-payment of invoices by customers.

“The porous municipal water reticulation infrastructure also creates a simulated shortage. We are working hard to assist and collaborate with municipalities through the competent leadership of our Minister to alleviate this challenge.”

In February this year, the water utility launched the 210ML/d Vlakfontein Reservoir in the City of Ekurhuleni. The reservoir is post-tensioned concrete, the biggest in the world and is portion of the Mapleton Booster scheme augmentation programme. – SAnews.gov.za

Read More at the Source

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: 2024, Ekurhuleni, Free State, infrastructure, micro, Mpumalanga, North West, SA News, Water

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Fun South African fact

    Dear Editor Fun South African fact: towns like Franschhoek and Stellenbosch are home to world-class wine farms set in stunning, scenic surroundings. Regards Aressa Smith In Response to/From: Luxury Properties Seized in New Lottery Crackdown

    27 January 2026
  • Condolences on the Passing of Lusanda Dumke

    Statement by Leander Kruger MPL – DA Buffalo City Constituency Leader: The Democratic Alliance in Buffalo City Metropolitan Municipality mourns the passing of Springbok Women’s rugby player and Mdantsane trailblazer, Lusanda Dumke, who lost her battle with cancer at the age of 28. South Africa has lost an exceptional athlete, a leader, and a source…

    17 December 2025
  • Rape Kits Delivered, But…

    Statement by Nicholas Gotsell MP – DA NCOP Member on Security & Justice: The DA can confirm that 2 840 rape kits arrived in Cape Town on Monday, following sustained DA oversight and pressure after multiple police stations across the Western Cape were found to be without this critical forensic evidence tool. While this delivery…

    17 December 2025

About Guest

Previous Post:Fuel, paraffin and gas prices set to increase
Next Post:Tarsus To Sell Vertiv Infrastructure Portfolio in Sub Saharan Africa, Under New Distribution Agreement

Reader Interactions

Comments

  1. Shadow Chaser

    4 September 2023 at 9:58 pm

    This is probably off-topic, BUT here goes: I see that MyZA operates a number of \’sections\’ dealing with News, Directory, Events and a Marketplace and I was wondering just how https://MyZA.co.za manages to keep the content fresh and growing? Do you have an army of employees?

  2. Shadow Gal

    4 September 2023 at 6:22 pm

    Russia: You have two cows. When you get sober you remember that the mafia took them away from you, so you actually have none.

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Reach Trust