You are here: Home / News / Auditor General gives damning report on police headquarters

Auditor General gives damning report on police headquarters

1 March 2024 by Guest

This was just hours after workers at the Telkom Towers office were evacuated after it was declared unfit for human use

  • The Auditor General’s office on Wednesday told Members of Parliament that it has been months since it first flagged problems with the police headquarters in Pretoria.
  • The building at Telkom Towers used as South African Police Service (SAPS) headquarters had to be evacuated this week following an inspection by labour department officials who were accompanied by police management and the Solidarity trade union.
  • The office was declared unfit for human use.
  • According to the Auditor General’s report, the remaining eight buildings in the complex have not been used since being purchased years ago, costing the government at least R592-million.
  • SAPS claims that Public Works never handed over the other buildings.

The national headquarters of SAPS in Pretoria have been declared unfit for human use and have also been flagged by the Auditor General this week.

The Telkom Towers complex was purchased by Public Works in April 2016 for nearly R700-million, according to the office of the Auditor General.

But nearly eight years later, the complex has been underutilised and staff were recently evacuated from the premises due to safety concerns.

A presentation to MPs on Parliament’s Portfolio Committee on Public Works and Infrastructure by the Auditor General on Wednesday revealed that only one of the nine buildings in the complex has ever been used by SAPS.

Eight of the buildings have been vacant, costing the government at least R592-million. This has been flagged by the Auditor General as a material irregularity.

Several MPs voiced concern that the matter had not been resolved despite them raising it on numerous occasions since 2019.

Just hours after the meeting in Parliament, SAPS released a statement confirming that staff had been evacuated from the only building it had been using at the Telkom Towers. The building will remain closed until further notice is given.

Table of Contents

Toggle
  • Auditor General flagged issues months ago
  • SAPS’s office of horrors
    • Share this

Auditor General flagged issues months ago

Meanwhile, in Parliament, the Auditor General noted that 12 material irregularities had been identified in its report. Of these, eleven caused significant financial losses while the 12th was the misuse of public land.

Londoloza Songwevu, a senior audit manager who led the presentation to the committee said that four of these irregularities have been resolved as well as one that wasn’t at Telkom Towers.

According to the Auditor General, the buildings were fully functional at the time of purchase and were meant to become the central headquarters for SAPS in Pretoria. The complex was intended to alleviate the pressure on the budget to lease private buildings.

Songwevu said service delivery had been affected. “Over and above those [financial] losses, service delivery is impacted in the sense that SAPS is unable to conduct their business as they would have envisaged when the move first came about,” he told MPs.

Songwevu said that they flagged the Telkom Towers as a material irregularity late last year but wanted to give the new director-general time to respond to the matter. He told MPs that they were also concerned about the increasing number of material irregularities.

At the end of the presentation, the Auditor General made a few recommendations, which included that the portfolio committee “evaluate and monitor the effectiveness of consequence management [disciplinary] systems employed by the departments and entities to deal with instances of material irregularities”.

Committee chair Nolitha Ntobongwana (ANC) said the information presented by the Auditor General would be included in the committee’s end of term “legacy report”.

Ntobongwana also referred to an oversight visit in 2022. At the time, the committee had raised concerns about officials being “underprepared” during their visit and denied entry into some of the offices.

SAPS’s office of horrors

The closure of the police headquarters happened after labour department officials accompanied by police management and Solidarity trade union officials visited the building on Tuesday.

Johan Böning, of Solidarity, in a statement, described the deplorable state of the SAPS office. He said they had received several complaints from police members. Some of the allegations included a lack of clean drinking water, poor and broken air conditioning and ventilation, broken and dirty toilets, closed and unmarked emergency exits, and broken lifts, among other issues.

In the statement after the office’s closure, police management claimed that their primary concern was the “well-being” of employees. And that it was on the instruction of National Commissioner General Fannie Masemola that all of the staff left the premises.

“SAPS is in continuous engagements with the Department of Public Works and Infrastructure whose responsibility is the repair and maintenance of state facilities,” Brigadier Athlenda Mathe said.

She said that arrangements are being made for the functions carried out at the building to be performed at alternative premises. She said that “core policing” had not been affected by the “temporary” closure.

In response to questions from GroundUp, Mathe on Friday, said that she was aware of the Auditor General’s findings. “However, the finding was vehemently opposed and rejected. It was not a deliberate act from SAPS to continue using the leased buildings instead of the state building [Telkom Tower],” she said.

“Unfortunately, only Telkom Towers North was said to be ready and a certificate of occupation as well as a certificate of compliance was issued to SAPS which led to the occupation of Telkom Towers North. The other buildings were never handed over to the SAPS,” she said.

She added that SAPS had written to Public Works several times requesting a Project Execution Plan relating to the other buildings. “To date the Project Execution Plan has yet to be received by SAPS from Public Works.”

This meant that the only building that was somewhat functional now has to remain closed until further notice due to it being unfit for purpose.

GroundUp sent questions to Public Works spokesperson Lennox Mabaso on Friday. The article will be updated with the department’s response once it is received.

© 2024 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.

Read More at GroundUp

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: 2024, African, Budget, business, Government, GroundUp, infrastructure, new, office, ONE, Parliament, Pretoria, SAPS, Water

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Older Persons Grants Land Today — No Need to Queue at Dawn

    Dear Editor, Older Persons grants are paid today, 30 October, under SASSA’s revised November payment schedule — with disability grants on Monday 2 November, children’s grants on Tuesday 3 November, and grants under review on Thursday 5 November. Two things every beneficiary should know. First, grant money does not expire on payment day. It stays…

    30 October 2026
  • November Grants Pay Early – No Need to Queue at Dawn

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. November grants pay earlier than usual. Older Persons grants are paid on Friday 30 October, Disability grants on 2 November, and Child Support and other grants on 3 November. Grants still under review are paid on 5 November. The money…

    27 October 2026
  • NSFAS 2027 applications close on 31 October — SASSA households, apply now

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. NSFAS applications for the 2027 academic year close on Friday 31 October 2026, and no extension is expected. If your household receives a SASSA grant, your child already passes the NSFAS financial eligibility test — but they still have to…

    25 October 2026

About Guest

Previous Post:128 Mpumalanga schools introduce coding, robotics  
Next Post:SA, Netherlands recommit to cooperation in water and sanitation sector

Reader Interactions

Comments

  1. Tse Tse Guy

    7 September 2026 at 1:21 pm

    Fun South African Fact: The world’s largest themed resort hotel in the world – The Palace of the Lost City – is found in South Africa. Surrounding the Palace is a 25 hectare manmade botanical jungle with almost 2 million plants, trees and shrubs.

  2. sick saurus

    4 September 2026 at 5:51 pm

    How many official languages are there in South Africa?

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Stratlec Online