• Skip to main content
  • Skip to header right navigation
  • Skip to after header navigation
  • Skip to site footer
MyZA

MyZA

News, Directory, Events and Other Stuff

  • Social Media
  • Sport
  • World News
  • Home
  • Submit News
  • Directory
  • Events
  • Stratlec
  • TFSA
  • News
    • APO
    • Today’s Sport News
    • Todays Social Media and Tech Headlines
    • Today’s World News
    • Today’s SA Financial News
  • Contact
You are here: Home / News / How SA’s Lesotho Water Project Costs Ballooned by R45-Billion

How SA’s Lesotho Water Project Costs Ballooned by R45-Billion

13 August 2025 by Guest

The second phase of the Lesotho Highlands Water Project has seen costs escalate from R8-billion in 2008 to R53-billion today, with delays pushing completion from 2019 to 2028

  • The second phase of the Lesotho Highlands Water Project has ballooned from R8-billion in 2008 to R53-billion, raising questions about governance and oversight.
  • Parliament’s Portfolio Committee on Water and Sanitation has criticised governance weaknesses and oversight gaps.
  • The Democratic Alliance has filed a public access to information request after the Department of Water and Sanitation failed to respond to its questions about the cost escalations.
  • Political and administrative delays, treaty complications, and changes in government leadership contributed to the massive cost increases, with more than R20-billion attributed to delays.

The cost of the second phase of the Lesotho Highlands Water Project (LHWP) to deliver water to South Africa’s industrial heartland and generate hydropower for Lesotho has increased by R45-billion.

In 2008, phase 2 was projected to cost R8-billion. By 2022, this had ballooned to R42-billion. It now stands at R53-billion, raising questions about governance, oversight and accountability.

“Despite Minister [Pemmy Majodina]’s public acknowledgement that a probe into the escalating costs of Phase 2 of the LHWP would be conducted, no further details have been shared with Parliament or the public,” Democratic Alliance (DA) deputy spokesperson on water and sanitation Stephen Moore noted in a statement issued by the party last week.

Moore has now filed a Promotion of Access to Information Act (PAIA) application to the Department of Water and Sanitation (DWS). This follows two unanswered letters, the first sent on 8 May.

DWS spokesperson Wisane Mavasa said the May letter was not sent directly to the minister or director general. “Unfortunately, the letter was not acted upon by the officials that it was sent to,” she said, adding that the minister would respond “shortly”.

DWS says the price escalation is the result of various factors, including years of delays, treaty complications and market fluctuations.

Regarding the DA’s PAIA application, Mavasa said the department has 30 calendar days to respond, and it would do so within the legal timeframe.

Table of Contents

Toggle
  • Oversight gaps
  • How R8-billion became R53-billion
  • Governance fixes and audits

Oversight gaps

The South African Portfolio Committee on Water and Sanitation raised concerns about the cost of the project with the Auditor-General of South Africa (AGSA) at a sitting on 6 May, chaired by the DA’s Leonard Basson.

The meeting flagged weaknesses in governance created by the dual-implementation model between the Trans-Caledon Tunnel Authority (TCTA) and the Lesotho Highlands Development Authority (LHDA).

Delays have pushed completion from 2019 to 2028, affecting the delivery schedule and future phases of the project.

The committee also noted constraints stemming from the 1986 treaty preventing AGSA from auditing LHDA directly, “leaving South Africa reliant on Lesotho’s audit structures”.

But, says Mavasa, the Lesotho Highlands Water Commission (LHWC), has equal representation from both governments, had “full access to the cost records of the LHDA”, and had received detailed information about the delays.

The committee also criticised the royalty arrangement, which it said obliges South Africa to continue payments to Lesotho even when water deliveries are interrupted.

Other concerns included limited local procurement, dominance of foreign contractors, and opaque financial flows.

Some MPs went as far as calling for an immediate funding suspension, citing mismanagement and treaty flaws.

However, AGSA cautioned against such a drastic move, warning of legal consequences. It recommended treaty reforms, including joint audits, instead.

Mavasa says South Africa and Lesotho have agreed to review the treaty, but the “matters for review” have yet to be decided. She said South Africa has already set up its review team. Submission of the Lesotho government’s team is awaited.

Lesotho’s Finance Minister Retšelisitsoe Matlanyane told Parliament in February that the government intended to pursue “the overdue review of the treaty” to negotiate a better deal for Lesotho.

How R8-billion became R53-billion

Mavasa outlined the project’s financial journey in detail. The original 2008 feasibility study produced a preliminary R8-billion estimate – excluding inflation, currency shifts, contingency allowances, and modern environmental and social safeguards.

Construction of the main works was expected to start in 2013 and deliver water to Gauteng by 2019. However, she said the main contracts were only awarded in 2022 because negotiations with Lesotho took longer than expected. The situation worsened with years of administrative and procedural delays.

“The Phase 2 agreement was signed in August 2011. It then took 14 months for the RSA Parliament to ratify the Phase 2 agreement and a further seven months for the Lesotho Parliament to ratify the agreement after the ratification by the SA Parliament,” said Mavasa.

After Lesotho’s 2013 change of government, the agreement was subjected to fresh scrutiny, adding further delays, according to Mavasa, who also pointed out that between 2013 and 2022, the DWS had five different ministers and 11 director-generals, a turnover that slowed decision-making.

There were also financing complications. Funders raised concerns over procurement processes for the main contracts and requested that they be tendered afresh. The covid pandemic also disrupted preparatory work, pushing back the award of main contracts.

In October 2022, the LHDA projected a R42-billion completion cost – incorporating contract prices, social and environmental programmes, foreign exchange effects, and administrative cost of managing the project.

More than R20-billion was due to inflation linked to the delays, said Mavasa.

In October 2024, the figure rose to R53-billion. The department attributed this to:

  • R4.2-billion from boosting the contingency provision in line with international good practice from R3.3-billion in 2022 to R7.5-billion in 2024.
  • R5.4-billion for additional social obligations requested by Lesotho, such as rural water supply and road infrastructure — not yet approved by the LHWC but included in the LHDA’s projections.
  • R1.7-billion in price escalations, design changes, and contractor claims linked to delays, including work-permit issues.

Governance fixes and audits

According to Mavasa, the project cost and time overruns have been a major concern for DWS and Minister Majodina. She said LHDA has developed a plan to minimise any further delays and cost overruns.

She said LHWC will appoint a multidisciplinary team of experts to conduct management audits of contracts.

Although the project is about 50% complete, she said two primary contracts are behind schedule. “However, the LHDA is executing a turnaround plan to avoid further delays and recover lost time.”

In 2024, Mavasa said the department had established a governance committee comprising the department, the TCTA, and the South Africa delegation to the LHWC, which meets monthly to review progress.

Mavasa said the DWS director-general and the principal secretary of the relevant department in Lesotho hold ad-hoc and quarterly meetings to address issues arising from the project. Unresolved issues are escalated to the ministers.

Lesotho Minister of Natural Resources Mohlomi Moleko said he could only respond next week as he is outside the country.

© 2025 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.

The 2019 elections saw increased participation from youth activists advocating for change.

Read More at the Source

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: 2024, ACT, Africa, African, agreement, CAN, GOOD, Government, GroundUp, infrastructure, Lesotho, Letter, Letters, Market, officials, Parliament, South Africa, study, Water

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Fun South African fact

    Dear Editor Fun South African fact: towns like Franschhoek and Stellenbosch are home to world-class wine farms set in stunning, scenic surroundings. Regards Aressa Smith In Response to/From: Luxury Properties Seized in New Lottery Crackdown

    27 January 2026
  • Condolences on the Passing of Lusanda Dumke

    Statement by Leander Kruger MPL – DA Buffalo City Constituency Leader: The Democratic Alliance in Buffalo City Metropolitan Municipality mourns the passing of Springbok Women’s rugby player and Mdantsane trailblazer, Lusanda Dumke, who lost her battle with cancer at the age of 28. South Africa has lost an exceptional athlete, a leader, and a source…

    17 December 2025
  • Rape Kits Delivered, But…

    Statement by Nicholas Gotsell MP – DA NCOP Member on Security & Justice: The DA can confirm that 2 840 rape kits arrived in Cape Town on Monday, following sustained DA oversight and pressure after multiple police stations across the Western Cape were found to be without this critical forensic evidence tool. While this delivery…

    17 December 2025

About Guest

Previous Post:US report highlights human rights crisis in South Africa
Next Post:Alleged Upington “Black Face” Incident

Reader Interactions

Comments

  1. Gov Skull

    15 August 2025 at 11:05 am

    Fun South African Fact: The Lion, the cheetah and the wildebeest are three of the five fastest animals in the world and they all live in South Africa.

  2. Noisy Girl

    13 August 2025 at 4:12 pm

    Shebeen – an unlicensed bar [sha-been] These are unlicensed bars usually found in low-income suburbs located outside of the major towns and cities, more commonly known as ‘the townships’.

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Reach Trust