You are here: Home / News / Major Eastern Cape water projects stalled over battle with small businesses

Major Eastern Cape water projects stalled over battle with small businesses

20 March 2026 by Guest

Two Whittlesea water treatment works were set to benefit nearly 30 villages

Work at the Bushmanskrantz Water Treatment Works has ground to a halt.

  • Two major water projects near Komani in the Eastern Cape have stalled because of a dispute over subcontracting small businesses.
  • Local businesses say they are not getting a fair share of the work on the Poplar Grove and the the Bushmanskrantz (Zweledinga) water treatment works.
  • The two projects are intended to benefit 30 villages, which are struggling with severe water shortages.

Two major water projects in Whittlesea, outside Komani in the Eastern Cape, have been halted since January because of a dispute over the subcontracting of small, local businesses.

The Poplar Grove and Bushmanskrantz (Zweledinga) water treatment works are meant to serve nearly 30 villages struggling with severe water shortages. Many rely on boreholes that often stand idle due to a lack of diesel.

“We are really struggling with water and we hoped these projects would help,” said Siyabulela Ningiza from Mchewula village. “Now they are closed and we don’t know when they will reopen. We have taps but they are dry.”

Both projects have faced repeated interruptions since construction began.

Work stopped in 2024 after residents protested, demanding jobs, but resumed once some villagers were hired. Then in June 2025, local business owners raised concerns about the share of work allocated to small, medium and micro enterprises (SMMEs).

Hewu Contractors Forum member Bongani Tabata said local businesses had applied for subcontracting opportunities but were overlooked. “None of the local small business owners were called for interviews. Instead, we saw a subcontractor already working on site,” he said.

He said the budget for Poplar Grove water treatment works, which started in August 2024, was R124-million, and for the Bushmanskrantz (Zweledinga) water treatment works, which started in November 2024, was R105-million. (Despite repeated inquiries, GroundUp was unable to confirm these figures with the municipality.)

Chris Hani District Municipality spokesperson Nangamso Ngceke said contractors are required to allocate 30% of the work to SMMEs, including subcontractors and local suppliers, but responsibility for appointing them “rests with the contractor”.

She confirmed the stoppage followed complaints from the forum and said the municipality is investigating.

Mcebisi Pala, CEO of ATG Tradings, the main contractor for Bushmanskrantz, said the site had been closed for safety reasons after workers were threatened and intimidated.

He said the process of appointing SMMEs has already been done and five subcontractors were appointed, and two are expected to be appointed at a later stage. He said the 30% allocation applied to small businesses across the Chris Hani district, not only those from the villages where the project is located.

Dave de Wet of Sinakho Consulting, the project’s consulting engineers, said the same – that SMMEs were appointed from the broader Chris Hani district.

But Pala disputed the claim, saying they had advertised what the project required, and the shortlisted applications were sent to the district municipality, “who selected the company to be appointed”.

Tabata said tenders were advertised twice, in August and October 2025. They had applied both times.

He said tensions rose when forum members discovered that a subcontractor working at the Bushmanskrantz site was not from the area.

But he denied that the forum had closed the construction sites.

“As community members we did not close the site. All we wanted was transparency because none of the people we know from our villages were appointed,” he said.

Work on the Poplar Grove Water Treatment Works is also stalled.

Tabata said the forum approached the district municipality, and a follow-up meeting was scheduled for 28 January. “Now the municipality is running away from us,” he said.

Ngceke confirmed the meetings and that the municipality had received a formal complaint from the Hewu Contractors Forum regarding SMME participation.

“However, subsequent developments occurred outside of the agreed process. The district municipality strongly condemns the manner in which this matter was handled,” she said. The municipality was trying to “secure a sustainable and lawful resolution” and to “accelerate the delivery of services to the intended communities”.

When GroundUp visited, both projects were closed and under security guards.

Thinasonke Maneli, a member of the project steering committee at Bushmanskrantz, said attempts since August to resolve the dispute had been unsuccessful.

 

© 2026 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.

 

Poor quality of teaching: Concerns about the quality of teaching in some schools.

Read More at the Source

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: 2024, Budget, business, CAN, community, Eastern Cape, GroundUp, Khomani, Komani, micro, Quuenstown, Running, Stage, Water

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Re: R8.5 Million Lotto Winner Claims Prize in Gqeberha

    Dear Editor This is indeed an exciting story for the community. Congratulations to the winner and may this bring positive change to Nomathamsanqa. As someone from KwaMashu, I understand the impact such winnings can have on township communities. Wishing the grandfather all the best. Regards Themba Zulu In Response to/From: R8.5 Million Lotto Winner Claims…

    18 September 2026
  • Re: Minister Tolashe and Postbank Black Cards

    Dear Editor I appreciate the Minister’s assurance regarding the smooth transition to Postbank Black Cards for grant beneficiaries. As a concerned citizen, I hope the government will ensure that all beneficiaries, especially elderly and vulnerable populations in areas like Soweto, receive adequate assistance during this transition period. The expansion of card replacement locations to include…

    18 September 2026
  • Lotto Winner Story

    Dear Editor This is indeed an exciting story for the community. Congratulations to the winner and may this bring positive change to Nomathamsanqa. Regards Willem Pieterse In Response to/From: R8.5 Million Lotto Winner Claims Prize in Gqeberha

    16 September 2026

About Guest

Previous Post:High-Level Intra-African Dialogue – ACCORD | SA News
Next Post:Who is Steve Motsumi? Mkhwanazi labels him ‘most feared’ criminal boss | SA News

Reader Interactions

Comments

  1. Married Man

    13 September 2026 at 8:23 am

    Why is gambling banned in South Africa?

    Because there are too many cheetahs.

  2. Nessie

    10 September 2026 at 3:47 am

    Archeologists in South Africa have just discoved what they think is the oldest tampon ever found

    They are trying to find out what period it came from.

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Stratlec Online