You are here: Home / News / R24-Million Spent on Indwe Stadium With Little to Show for It

R24-Million Spent on Indwe Stadium With Little to Show for It

14 April 2025 by Guest

Two contractors later, the stadium is far from complete

Emalahleni Local Municipality has spent R23.8-milllion on this sports stadium, which it says will be complete by June.

Seven years after the Emalahleni Local Municipality paid a contractor R10-million to build a sports stadium, the project is still unfinished and the Hawks are in the “initial stage” of a fraud and corruption investigation.

The construction of the Indwe Sports Stadium was supposed to take 18 months and cost R11-million. But to date R23.8-million has been spent and there is little progress.

In July 2018 MBS Civils JV Cudjor Quantity Surveying was awarded the tender and paid R10-million. But less than a year later, the company abandoned the site having built only a small wall.

The Hawks are investigating a case of fraud and corruption, but the investigation is still in its “initial stages”, Hawks spokesperson Ndiphiwe Mhlakuvana told GroundUp.

Emalahleni Local Municipality spokesperson Luthando Nqumkana said no other action has been taken against the contractor. Nor have there been any efforts to recover the spent funds.

MBS Civils could not be reached for comment.

A new tender was awarded in 2023 for R14.5-million, this time to MVI Construction and Maintenance. The contract was for 12 months to finish the stadium, with a netball court, rugby field and soccer field.

But when GroundUp visited the site in March, there was little progress. We did not see any work happening on the site. Floodlights have been installed, but the only building is a changeroom without windows or doors. There are no usable sports facilities and no grandstands.

Nqumkana told GroundUp that the contractor is now on site but acknowledged that progress is slow. He said R12.8-million has been spent on this new tender (excluding the R11-million previously paid to MBS Civils), and that the project is scheduled to be completed by June this year.

Community members are becoming increasingly frustrated with the project. “After the first contractor left, nothing happened. When the second contractor started, it first destroyed the walls built by the first contractor and continued with the work, to prove that the first contractor was paid for nothing,” said community leader Transkei Mjongile.

Another community leader Thabo Khethi said, “The contractor is on and off, they come for a few months then leave and come back again. We don’t know what is happening here.”

“This frustrates us a lot … We want to see our town developed like other small towns but the only thing we see is millions spent with no end results.”

© 2025 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.

Read More at GroundUp

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: CAN, community, Community Leader, Fraud, GroundUp, march, Netball, new, Rugby, show, Stage, Transkei

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Older Persons Grants Land Today — No Need to Queue at Dawn

    Dear Editor, Older Persons grants are paid today, 30 October, under SASSA’s revised November payment schedule — with disability grants on Monday 2 November, children’s grants on Tuesday 3 November, and grants under review on Thursday 5 November. Two things every beneficiary should know. First, grant money does not expire on payment day. It stays…

    30 October 2026
  • November Grants Pay Early – No Need to Queue at Dawn

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. November grants pay earlier than usual. Older Persons grants are paid on Friday 30 October, Disability grants on 2 November, and Child Support and other grants on 3 November. Grants still under review are paid on 5 November. The money…

    27 October 2026
  • NSFAS 2027 applications close on 31 October — SASSA households, apply now

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. NSFAS applications for the 2027 academic year close on Friday 31 October 2026, and no extension is expected. If your household receives a SASSA grant, your child already passes the NSFAS financial eligibility test — but they still have to…

    25 October 2026

About Guest

Previous Post:Parental Burnout: Recognising the Signs and How to Recover
Next Post:Deadly HeadachesDeadly headaches | Carte Blanche | M-Net

Reader Interactions

Comments

  1. Sky Dahlia

    7 September 2026 at 4:04 pm

    Fun South African Fact: South Africa is the Rainbow Nation.

  2. Trinitysoul

    5 September 2026 at 4:01 pm

    At the end of the school year and a mother asked his son if the exam questions were difficult. And he answers her saying “They weren’t bad at all,” it was the answers that gave me all the trouble.

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Stratlec Online