You are here: Home / News / ‘The conclude of load shedding is indeed in sight’ – Ramakgopa

‘The conclude of load shedding is indeed in sight’ – Ramakgopa

14 February 2024 by Guest

‘The end of load shedding is indeed in sight’ – Ramakgopa

Minister in the Presidency for Electricity, Dr Kgosientsho Ramokgopa, says despite “obstacles, uncertainties and temporary setbacks”, the end of load shedding is in sight.

He was addressing the State of the Nation Address (SONA) debate held at the Cape Town City Hall on Tuesday.

“[The] path to achieving a stable and sustainable energy landscape has been fraught with obstacles, uncertainties, and temporary setbacks and yet, with each passing day, we continue to register progress as we chart the path to energy security.

“The end of load shedding is indeed in sight; the future is bright,” he said.

Eskom power stations

The Minister explained the steps government, in cooperation with Eskom, has taken to urgently address the energy challenge in the country including returning units to service on time or earlier and bolstering new generation capacity.

“Units 1 to 3 of Kusile [Power Station], which had been out of service since October of 2022, were successfully returned ahead of schedule. As planned, Unit 5 was synchronised to the grid in December 2023, contributing 800MW. The four Kusile Units collectively injected 3200MW of capacity into the grid.

“Medupi [Power Station] Unit 4 will return to service this year in September, a year ahead of schedule. Kusile Unit 6 will be synchronised in late November 2024. These units will add 1600MW to the grid. In addition, Unit 2 of Koeberg [Power Station] will return to service in September 2024, giving us 980MW following a planned outage. These interventions will collectively add 2580MW to the grid in 2024. The end of load shedding is indeed within sight,” he said.

Added to this, Eskom’s rigorous maintenance plan for power stations has been implemented, which Ramokgopa said is expected to ensure that “going into the winter of 2024, the fleet’s reliability will have been significantly strengthened”.

“This also means that heading into the winter peak demand period, we can claw back up to 2 000MW by tapering planned maintenance and strengthening available capacity.

“From March of 2024, we will begin reducing planned maintenance from the current 6 000MW to 5 000MW in April 2024 and to around 3 500MW in May 2024, a threshold that will be sustained during the winter demand period,” he said.

New generation capacity

Ramokgopa revealed that to further bolster future energy security, Eskom is in the process of appointing a team which is expected to “undertake a procurement process for partners to develop the Richards Bay Closed Cycle Gas Turbine”.

This is a plan to yield a further 3 000MW for the grid.

Furthermore, the procurement of nuclear energy is also on the table.

“Gas will increasingly feature prominently in our short- to medium-term base load requirements. Eskom is working on converting Gourikwa and Ankerlig [power stations] to gas from diesel on the Open Cycle Gas Turbine (OCGT) technology. This initiative is anticipated to yield an additional 2 000MW, with a further 1 000MW expected from the conversion to Closed Cycle Gas Turbines (CCGT).

“[Government] will commence the procurement process of an additional 2 500MW of new nuclear capacity this year on an affordable scale and pace basis, as well as 1 500MW of pump storage facility at Tubatse in Limpopo,” Ramokgopa said. – SAnews.gov.za

NeoB
Wed, 02/14/2024 – 10:42

253 views

Minister in the Presidency for Electricity, Dr Kgosientsho Ramokgopa, says despite “obstacles, uncertainties and temporary setbacks”, the terminate of load shedding is in sight.

He was addressing the State of the Nation Address (SONA) debate held at the Cape Town City Hall on Tuesday.

“[The] path to achieving a stable and sustainable energy landscape has been fraught with obstacles, uncertainties, and temporary setbacks and yet, with each passing day, we continue to register progress as we chart the path to energy security.

“The pause of load shedding is indeed in sight; the future is sparkling,” he said.

Eskom power stations

The Minister explained the steps government, in cooperation with Eskom, has taken to urgently address the energy challenge in the country including returning units to service on time or earlier and bolstering modern generation capacity.

“Units 1 to 3 of Kusile [Power Station], which had been out of service since October of 2022, were successfully returned ahead of schedule. As planned, Unit 5 was synchronised to the grid in December 2023, contributing 800MW. The four Kusile Units collectively injected 3200MW of capacity into the grid.

“Medupi [Power Station] Unit 4 will return to service this year in September, a year ahead of schedule. Kusile Unit 6 will be synchronised in tardy November 2024. These units will add 1600MW to the grid. In addition, Unit 2 of Koeberg [Power Station] will return to service in September 2024, giving us 980MW following a planned outage. These interventions will collectively add 2580MW to the grid in 2024. The finish of load shedding is indeed within sight,” he said.

Added to this, Eskom’s rigorous maintenance situation for power stations has been implemented, which Ramokgopa said is expected to ensure that “going into the winter of 2024, the fleet’s reliability will gain been significantly strengthened”.

“This also means that heading into the winter peak demand period, we can claw back up to 2 000MW by tapering planned maintenance and strengthening available capacity.

“From March of 2024, we will open reducing planned maintenance from the current 6 000MW to 5 000MW in April 2024 and to around 3 500MW in May 2024, a threshold that will be sustained during the winter demand period,” he said.

Modern generation capacity

Ramokgopa revealed that to further bolster future energy security, Eskom is in the process of appointing a team which is expected to “undertake a procurement process for partners to develop the Richards Bay Closed Cycle Gas Turbine”.

This is a situation to yield a further 3 000MW for the grid.

Furthermore, the procurement of nuclear energy is also on the table.

“Gas will increasingly feature prominently in our short- to medium-term base load requirements. Eskom is working on converting Gourikwa and Ankerlig [power stations] to gas from diesel on the Open Cycle Gas Turbine (OCGT) technology. This initiative is anticipated to yield an additional 2 000MW, with a further 1 000MW expected from the conversion to Closed Cycle Gas Turbines (CCGT).

“[Government] will commence the procurement process of an additional 2 500MW of novel nuclear capacity this year on an affordable scale and pace basis, as well as 1 500MW of pump storage facility at Tubatse in Limpopo,” Ramokgopa said. – SAnews.gov.za

Read More at the Source

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: 2024, Cape Town, Energy, Eskom, Government, Limpopo, new, Richards Bay, SA News, Technology

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Older Persons Grants Land Today — No Need to Queue at Dawn

    Dear Editor, Older Persons grants are paid today, 30 October, under SASSA’s revised November payment schedule — with disability grants on Monday 2 November, children’s grants on Tuesday 3 November, and grants under review on Thursday 5 November. Two things every beneficiary should know. First, grant money does not expire on payment day. It stays…

    30 October 2026
  • November Grants Pay Early – No Need to Queue at Dawn

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. November grants pay earlier than usual. Older Persons grants are paid on Friday 30 October, Disability grants on 2 November, and Child Support and other grants on 3 November. Grants still under review are paid on 5 November. The money…

    27 October 2026
  • NSFAS 2027 applications close on 31 October — SASSA households, apply now

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. NSFAS applications for the 2027 academic year close on Friday 31 October 2026, and no extension is expected. If your household receives a SASSA grant, your child already passes the NSFAS financial eligibility test — but they still have to…

    25 October 2026

About Guest

Previous Post:The Importance of Garage Door Repairs and Automation
Next Post:Roses are red, violets are blue – but watch out for these relationship red flags, too!

Reader Interactions

Comments

  1. santas little helper

    28 August 2026 at 4:17 pm

    I thought I wanted a job, turns out I really just wanted a paycheck

  2. Dorothy Solitaire

    25 August 2026 at 9:22 pm

    Fun South African Fact: For an unforgettable bucket-list activity, search for the famous Big 5 (lion, leopard, elephant, rhino and buffalo) on safari in one of South Africa’s national parks or private game reserves. A South African safari is an experience like no other!

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Stratlec Online