How Not to Build a Stadium

26 September 2025 by Guest

Tens of millions have been spent on a stadium in Elim since 2017. The stadium is still not complete.

The Waterval Sports Facility has been standing unused for years after work on the football field and athletics track stalled.

  • A sports stadium in Waterval, near Elim, stands incomplete and unused, eight years after construction began.
  • R40-million has been spent on the project, according to the Makhado Municipality’s annual reports.
  • The football field and athletics track are yet to be finished and none of the completed facilities are being used.
  • The current contractor says it aims to complete the work by the end of October.

Eight years after construction began on the Waterval Sports Facility near Elim, it is still not complete. The Makhado Municipality has spent about R40-million on the project, according to annual reports.

The project was meant to transform a local field into a stadium capable of hosting tournaments. Construction started in 2017. Changing rooms, a guard house, a 2,000-seater pavilion and tennis courts were built after multiple delays. But the football field and athletics track are still not ready to use and none of the other facilities are being used.

The current contractor, Mvuno Geo-environmental Civil and Construction, is responsible for finishing the field and track. Grass seedlings were planted on the football pitch last year, but weeds started to outgrow the grass. New grass is now being planted, using a sodding method. The athletics track still needs to have its top, all-weather surface laid.

Mvuno’s site manager Vincent Mutsila said they are waiting for imported materials for the track. “We expect to finish by the end of October, depending on when the materials arrive,” he said.

Local footballer Victor Chabalala, of local football team 7 Stars, says the delays are affecting young players. While they wait for the sports facility to be completed, they train on a dusty field.

“Our boots and balls wear out fast, and there’s no security,” said Chabalala. “When we play away on proper fields, it’s a big adjustment. We’d be very happy if the stadium were finally finished.”

On 16 September, the EFF led a march to the municipal offices in Waterval to hand over a memorandum of demands. Residents called for answers on when the stadium will be completed. The memo warned that the community might take matters into their own hands if nothing was done.

The project has been funded mainly through the Municipal Infrastructure Grant (MIG), with top-ups from the municipality.

According to the municipality’s annual reports, R7.5-million was spent on the project in 2018/19, R10.9-million in 2019/20, and R16.5-million in 2020/21. The municipality did not receive clean audit opinions in any of these years, so the expenditure figures should be treated with caution.

In 2021, the project stalled. The annual reports provide various reasons for the delays, including the covid pandemic and delays in sourcing materials. The 2023/24 annual report notes that the contractor was charged penalties for missing the deadline and was eventually terminated.

Diges Group, the contractor originally responsible for the running track, football pitch, and a borehole, told the Limpopo Mirror in 2023 that they completed what was practically possible, but could not finish it because other contractors and the municipality first had to complete the electric connection and installation of the pavilion, which was not done in time. The material for the running track expired before it could be used.

Mvuno Geo-environmental Civil and Construction was appointed to finish the project, and another R4-million was allocated in the 2024/25 financial year, which ended on 30 June. No additional money was allocated for the 2025/26 financial year.

In May 2024, then municipal spokesperson Louis Bobodi promised the stadium would be ready by June. On 22 August this year, we asked the new spokesperson, Mpho Rathando, for details on costs, delays, and outstanding work. Despite repeated follow-ups, the only response so far has been: “The municipality will comment once the project is completed.”

Published with the Limpopo Mirror.

© 2025 GroundUp. This article is licensed under a Creative Commons Attribution-NoDerivatives 4.0 International License.

You may republish this article, so long as you credit the authors and GroundUp, and do not change the text. Please include a link back to the original article.

We put an invisible pixel in the article so that we can count traffic to republishers. All analytics tools are solely on our servers. We do not give our logs to any third party. Logs are deleted after two weeks. We do not use any IP address identifying information except to count regional traffic. We are solely interested in counting hits, not tracking users. If you republish, please do not delete the invisible pixel.

School violence: Bullying, fights, and other forms of violence in schools.

Read More at the Source

Share this:

  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Print (Opens in new window) Print
  • Email a link to a friend (Opens in new window) Email
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Share on Tumblr (Opens in new window) Tumblr
  • Share on WhatsApp (Opens in new window) WhatsApp
  • Share on Mastodon (Opens in new window) Mastodon
Category: NewsTag: 2024, Athletics, CAN, community, Connection, EFF, Football, GroundUp, infrastructure, Limpopo, Makhado, march, Money, new, Running, Sports, Tennis, UPS, Weeds

If you feel strongly about this article then feel free to send MyZA a ‘Letter to the Editor’ using the submission form below:


Letter to the Editor

This field is for validation purposes and should be left unchanged.
If this is in response to an article please include that article title here or as the lead in for the first paragraph of your Letter below.

Separate tags with commas

Localise your letter by naming the city your words are about. Add relevant words describing your subject. Single comma separated words of no more than 5
Your Name(Required)
Your Name will be linked to the website below.
Your personal, business or social media web site
Choose NO to not set up a user account on MyZA. User Accounts will allow you to submit letters under your own Author Name

3 Latest Letters to the Editor:

  • Older Persons Grants Land Today — No Need to Queue at Dawn

    Dear Editor, Older Persons grants are paid today, 30 October, under SASSA’s revised November payment schedule — with disability grants on Monday 2 November, children’s grants on Tuesday 3 November, and grants under review on Thursday 5 November. Two things every beneficiary should know. First, grant money does not expire on payment day. It stays…

    30 October 2026
  • November Grants Pay Early – No Need to Queue at Dawn

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. November grants pay earlier than usual. Older Persons grants are paid on Friday 30 October, Disability grants on 2 November, and Child Support and other grants on 3 November. Grants still under review are paid on 5 November. The money…

    27 October 2026
  • NSFAS 2027 applications close on 31 October — SASSA households, apply now

    Dear Editor, I run SAGrant (sagrant.co.za), a free resource helping South Africans navigate SASSA grants. NSFAS applications for the 2027 academic year close on Friday 31 October 2026, and no extension is expected. If your household receives a SASSA grant, your child already passes the NSFAS financial eligibility test — but they still have to…

    25 October 2026

About Guest

Previous Post:Statement on the Resignation of NLC Chairperson Barney Pityana
Next Post:Tshwane Speaker Disregards Sinkholes

Reader Interactions

Comments

  1. Poppin Loot

    2 September 2026 at 1:21 am

    Vatican City: You have two cows. They were both taken advantage of as calves.

  2. Trash

    27 August 2026 at 9:56 pm

    Vatican City: You have two cows. They were both taken advantage of as calves.

Copyright © 2026 · MyZA · All Rights Reserved · Powered by Stratlec Online